| Ticket | Description |
| ENH-2592 |
BUP applications will no longer hide most completed required action buttons. The only required actions that will be hidden are those hidden in the create account checklist |
| Upcoming: Enhanced Joint Owner Approval Process |
Upcoming: Enhanced Joint Owner Approval Process This is planned for release to UAT on May 14, and Production June 26 |
| Upcoming: Multiple Joint Owners |
Upcoming: Multiple Joint Owners Better serve the needs of your customers, particularly families, by supporting multiple owners on an account. Multiple Joint Owners supports the ability to add additional owners to consumer accounts post-booking through self-serve and the MANTL Console based on the configuration of your institution. Learn how to configure Multiple Joint Owners here. Note: Core testing by your institution should be done prior to enabling in Production and Sendgrid updates are recommended. This is planned for release to UAT on May 14, and Production June 26 |
|
Data Changes |
|
|
Reminder DENG - 4873 |
New metrics and filters will be made available in the existing KYC Dashboard to provide insights into your KYC process. Metrics
Filters
The dashboard also enables cross filtering where users can select a data point in one dashboard tile to have all dashboard tiles automatically filter on that value. These changes will go to UAT on April 24th and PROD on May 8th. |
|
Reminder DENG-3626 |
Update to add a column containing the notes recorded on a manual funding transaction. The new column will be added to the Simplified Funding Report, Simplified Business Applications Report, and Simplified Consumer Applications Report.
This will be released to UAT 5/8 and Production on 5/27 |
|
Reminder DENG-3690 |
The Role Changes Report has been modified to include changes to users' roles. Following the change, the additions and removals of users from a role will be captured in the report with the "Event Name" UserRolesUpdated. To provide data for these events, the following four columns will be added to the end of the report: